B is correct here:
transfers ownership of the products to the customer and terminates the responsibility of the project
management team.
reference prince2 - 20.3
The project's products must be passed to an operational and maintenance environment prior to the project being closed. This may happen as a single release at the end of the project, or the project approach may include phased delivery where products are handed over in a number of releases.