Question #: 14
Topic #: 1
[All PRINCE2-Foundation Questions]

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

  • A. Checkpoint Report
  • B. Highlight Report
  • C. Issue Report
  • D. Product Status Account
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Jasonbahr
Highly Voted 3 years, 7 months ago
issue report: A report containing the description, impact assessment and recommendations for a request for change, offspecification or a problem/concern . It is created only for those issues that need to be handled formally.
upvoted 6 times
...
a2d1fd1
Most Recent 7 months, 3 weeks ago
Selected Answer: C
C is correct, an issue report implies an issue is being dealt with formally.
upvoted 1 times
...
missmanou
2 years, 8 months ago
C is correct
upvoted 1 times
...
peppe
3 years, 1 month ago
correct c
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other