During stage 3, the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered. What should project assurance do next?
A.
Update the team plan to show that the work package is complete.
B.
Check the work package and follow the procedure to deliver completed products.
C.
Verify that all the products to be delivered by the work package are approved.
D.
Update the stage plan to show the work package as completed.
In PRINCE2, the role of project assurance includes ensuring that the products produced by the work packages are of the required quality and meet the defined criteria for approval. Therefore, when the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered, the project assurance should verify that all the products to be delivered by the work package have been reviewed and approved before they are formally accepted and used in the project.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
ravi_aws
1 year, 1 month agoanti8
2 years, 10 months agolovelifeysl_2021
3 years agosunee
3 years, 8 months ago