Question #: 19
Topic #: 10
[All PRINCE2-Practitioner Edition 6 Questions]

The project board has asked user and supplier assurance to review all product descriptions relating to the 'updated corporate quality procedures', prior to authorizing the stage plan for stage 3.
Is this appropriate as part of the 'directing a project' process, and why?

  • A. Yes, because project assurance should assess whether all stakeholders have been identified, if requested by the project board.
  • B. Yes, because project assurance should review the stage 3 plan for viability, if requested by the project board.
  • C. No, because the project manager is responsible for writing product descriptions when creating the stage 3 plan.
  • D. No, because the project board should review new product descriptions before they authorize the stage 3 plan.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
sunee
Highly Voted 3 years, 8 months ago
B is correct answer. Ref. 15.4.3 3rd paragraph
upvoted 6 times
...
mcesarlara
Most Recent 4 months, 1 week ago
Selected Answer: B
B. Correct. Project assurance is responsible for providing independent assurance on the viability and correctness of the stage plans. Reviewing product descriptions as part of the stage plan for stage 3 falls within this remit, ensuring that the descriptions are clear, complete, and meet the project's quality requirements. D. Incorrect. The project board relies on project assurance to provide an independent review of the project documents, including product descriptions. The project board does not typically engage in the detailed review of product descriptions but rather makes decisions based on the assurance provided by the project assurance roles.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
B Project Assurance has a role in advising on the selection of development strategy, design, and methods, and ensuring that any supplier and operating standards defined for the project are met2. In this context, if the Project Board requests it, Project Assurance should review all product descriptions relating to the ‘updated corporate quality procedures’ as part of their review of the stage 3 plan for viability. This helps ensure that the products will meet their intended purpose and that the project remains viable. So, it’s appropriate as part of the ‘Directing a Project’ process.
upvoted 1 times
...
PieroBe
1 year, 4 months ago
Selected Answer: B
B is correct one (ref 15.4.3)
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...