The project is part of a program to increase the number of ABC courses that respond to legislation. The program manager has instructed the project manager to deliver the 'e-learning course' incrementally. The project manager has asked the program manager how often the highlight reports are required, and what format the reports should be presented in.
Is this an appropriate approach to controlling progress, and why?
McDope
5 months, 1 week agoManikRoy
1 year, 1 month agoManikRoy
1 year, 1 month agoPieroBe
1 year, 4 months agoMohammed213
1 year, 4 months agoameyaengg
2 years, 2 months agowindy1
3 years, 8 months ago