During the 'starting up a project' process, the project manager discusses the standard model for course development with the executive. The project manager then assesses how the Health and Safety Training Project will be delivered, including what products should be delivered in each stage.
Is this an appropriate way to carry out the 'plan the initiation stage' activity, and why?

  • A. Yes, because the work of the initiation stage needs to be planned and approved, in the same way as other project work.
  • B. Yes, because the management controls for the initiation stage need to be defined and approved by the project board.
  • C. No, because subsequent stages are planned in the initiation stage as part of creating the project plan.
  • D. No, because the senior supplier is responsible for assessing the viability of the project approach.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
nai
Highly Voted 3 years, 9 months ago
C should be correct answer.
upvoted 6 times
...
ManikRoy
Most Recent 1 year, 1 month ago
Selected Answer: C
No, because subsequent stages are planned in the initiation stage as part of creating the project plan.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
C. No, because subsequent stages are planned in the initiation stage as part of creating the project plan. The statement in the scenario indicates that the project manager is assessing how the Health and Safety Training Project will be delivered, including what products should be delivered in each stage during the "starting up a project" process. This approach is not appropriate because the "starting up a project" process is primarily focused on the pre-project activities necessary to prepare for the initiation stage.
upvoted 1 times
...
PieroBe
1 year, 4 months ago
Selected Answer: C
The products to be delivered in each stage are only understood and plan in the Initiating a Project process (specifically during the "Create the Project Plan" activity).
upvoted 2 times
...
MortenC
1 year, 9 months ago
Selected Answer: A
A is correct because you have to have a stage plan for initiating a project
upvoted 3 times
...
windy1
3 years, 8 months ago
Page 176.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...