Exam PRINCE2-Practitioner topic 10 question 22 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 22
Topic #: 10
[All PRINCE2-Practitioner Edition 6 Questions]

MANAGING PRODUCT DELIVERY -
Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the 'classroom-based training material' discovered that the representatives assigned to check the products were unsuitable.
Which action should the team manager take in response?

  • A. Discuss the situation with project assurance.
  • B. Advise the project manager of this risk.
  • C. Update the quality register with these concerns.
  • D. Raise an exception report to the project manager.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: A
Option A is correct - Discuss the situation with project assurance. Refer 18.4.1 in the manual. Consult with project assurance as to whether any extra reviewers are required and ensure that the quality register is updated accordingly.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
Updating the quality register with these concerns [C] is not the appropriate action in this situation, as the quality register is used to record the quality criteria and standards that will be used to judge the quality of the project's products. Discussing the situation with project assurance [A] is not necessary at this stage, as the issue can be resolved by advising the project manager of the risk. Raising an exception report to the project manager [D] is not appropriate in this situation, as the issue is not out of tolerance and does not require the project manager to make a decision on how to proceed.
upvoted 1 times
ravi_aws
1 year, 1 month ago
B is correct
upvoted 1 times
...
...
timedout
3 years, 1 month ago
Sorry my below comment is incorrect, see table 8.1 "Project Assurance" (not 11.2)
upvoted 1 times
...
timedout
3 years, 2 months ago
Another ref is Table 11.2 "Project Assurance"
upvoted 2 times
...
pollon
3 years, 3 months ago
B is wrong - this is not a risk, it is an issue. A is correct - Ref C.6.1
upvoted 1 times
...
RajPathak
3 years, 9 months ago
it should be A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.