While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable. Which 2 actions should the Team Manager take in response to this situation?
A.
Consult the Senior Supplier to assign suitable reviewers.
B.
Discuss the situation with Project Assurance and agree the changes or additions to the reviewers. Advise the Project Manager of this risk.
C.
Ensure the Quality Register is updated with details of the agreed amendments to the reviewers.
D.
Notify the Project Manager by raising an Exception Report explaining that the original reviewers are unsuitable.
18.4.1
Undertake a review of the risks against the team plan, and advise the project manager of any additional or modified risks.
Consult with project assurance as to whether any extra reviewers are required and ensure that the quality register is updated accordingly.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
ManikRoy
1 year, 1 month agoRajPathak
3 years, 9 months ago