Exam PRINCE2-Practitioner topic 2 question 12 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 12
Topic #: 2
[All PRINCE2-Practitioner Edition 6 Questions]

CLOSING A PROJECT -
The Health and Safety Training Project is part of a strategic program for ABC. The updated benefits management approach needs to be checked when the products are being handed over. This check should ensure that it includes appropriate activities to assess whether the actual course sales meet the agreed forecast in the business case.
Which role should undertake this review as part of the 'closing a project' process?

  • A. Program management.
  • B. Project board.
  • C. Project manager.
  • D. Project assurance.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: D
Table 20.3, page 265, Its clear that the correct answer is project assurance - Option D. Project board does review the benefit management approach but in some other process, note the use of parenthesis (R) explained just below the table. As part of 'Closing a Project' process, the benefit management review is responsibility of project assurance.
upvoted 3 times
...
ravi_aws
1 year, 1 month ago
As part of the 'closing a project' process, the updated benefits management approach needs to be checked to ensure that it includes appropriate activities to assess whether the actual course sales meet the agreed forecast in the business case . Therefore, the role that should undertake this review is the Project Board, which is responsible for ensuring that the project remains viable and that the expected benefits are realized . The Project Board is also responsible for approving the updated benefits management approach and ensuring that it is aligned with the business case . Therefore, option B, "Project board," is the most appropriate answer.
upvoted 1 times
...
chriscilia81
1 year, 2 months ago
Selected Answer: C
C is correct. Question mentions '...needs to be checked when products are being handed over' therefore it relates to Closing of Project Process - refer to Figure 20.1 which shows that the last task under Closing a Project process is 'recommend project Closure', which is then approved/rejected under the 'Directing a Project' Process. If Rejected, the Closing Project process will restart, if not the project is considered closed for the PM team. Also, 20.4.1 'Before closure of ther project can be recommended, the PM must ensure (check) that the expected results have all been achieved and delivered'.
upvoted 1 times
...
ManikRoy
1 year, 2 months ago
Selected Answer: B
As per table 20.3 Page 265 the reviewers for benefit management approach are Executive, senior user, senior supplier, Project assurance. So the answer could be either B or D. What am i missing? why every answer is so confusing
upvoted 2 times
ManikRoy
1 year, 1 month ago
No that I revisited the table 20.3, page 265, Its clear that the correct answer is project assurance - Option D. Project board does review the benefit management approach but in some other process, note the use of parenthesis (R) explained just below the table. As part of 'Closing a Project' process, the benefit management review is responsibility of project assurance.
upvoted 1 times
...
...
georgio1974
1 year, 3 months ago
Selected Answer: D
D is correct as per Table 20.3 page 265
upvoted 2 times
...
ShiroKurtia
1 year, 3 months ago
Selected Answer: D
Should be D In 20.4.3 Table 20.3 Says: Benefits management approach - Review in the Project assurance column
upvoted 1 times
...
PieroBe
1 year, 4 months ago
Selected Answer: D
The answer is D (ref. table 20.3). The keyword here is "review", most of the reviews are entitled to the Project Assurance.
upvoted 3 times
...
schris
2 years, 1 month ago
According to table 20.3 on page 265, Project Manager is responsible for benefit management approach in "Hand over products", therefore C should be correct.
upvoted 2 times
...
ameyaengg
2 years, 2 months ago
A is correct
upvoted 1 times
...
nai
3 years, 9 months ago
B ref table 20.3
upvoted 2 times
...
Hazemsh
3 years, 10 months ago
A is correct . Ref 20.5.4.4 closing a project within programme
upvoted 3 times
windy1
3 years, 8 months ago
if it is part of program then A, otherwise should be B
upvoted 2 times
...
ManikRoy
1 year, 2 months ago
Though i selected B, but now i think A is the correct answer as this project is under a Programme. Thanks.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...