Question #: 23
Topic #: 9
[All PRINCE2-Practitioner Edition 6 Questions]

The senior user is concerned that the trainers' limited availability could delay their accreditation. This was discussed during the 'starting up a project' process, but during the 'initiating a project' process the project manager notices that it has not been recorded.
Which action should the project manager take FIRST?

  • A. Add appropriate activities to the project plan to manage the concern and avoid any adverse impact.
  • B. Raise an exception report to manage the impact that any such delay would have on the project plan.
  • C. Raise an issue report so that the trainers' time can be allocated to the accreditation activities.
  • D. Add the information to the risk register so that it can be evaluated and an action decided.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Ciluba
Highly Voted 3 years, 11 months ago
Correct Answer should be D - Page 226 Section 17.4.6
upvoted 5 times
...
ManikRoy
Most Recent 1 year, 1 month ago
Selected Answer: D
The identified risk need to be registered and then assessed and action planned.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
D. Add the information to the risk register so that it can be evaluated and an action decided. In PRINCE2, when a concern or issue is identified, the first step is typically to record it in the risk register. This allows for a structured evaluation of the concern, including its potential impact, probability, and any potential mitigation or response actions.
upvoted 1 times
...
PieroBe
1 year, 4 months ago
Selected Answer: D
This is clearly a risk as the impact is not certain. First risks need to be identified and assessed and only after we can plan how to cope with them.
upvoted 1 times
...
M477001
1 year, 7 months ago
Selected Answer: A
The question states it is during the initiating a project process. Page 208 section 16.4.7 for 'Create the project plan', "identify and confirm resources required. Confirm the selected people's availability".
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...