Which product should show that the project has been closed prematurely and has not achieved the objectives defined in the Project Initiation Documentation (PID)?
B
an Exception Report is used to document issues that are causing a project to veer off track1. It’s typically produced when a stage plan or project plan is forecast to exceed tolerance levels set2. However, the Exception Report is more about identifying the issue and offering options and recommendations for how to proceed2.
On the other hand, the End Project Report provides a summary of how the project performed against its original objectives, benefits, costs, and tolerances3. If a project is closed prematurely, this report should show the reasons for the closure and the extent to which the project objectives were met or not met
Problem with B option is, when the end project report is created, the project closure hasn't been approved.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
ravi_aws
1 year, 1 month agoGSD547
2 years, 7 months agoCiluba
3 years, 11 months ago