Which of the following management products ARE updated as part of Managing a stage boundary? 1. Business Case 2. Benefits Review Plan 3. Configuration Item Records 4. Project Brief
A is the correct answer. Benefits management approach is updated in the Activity Update the business case - see Figure 19.4
After the Project Startup, the contents of the Project Brief are extended and refined into the PID via the initiating a project process ( page 167). So Project Brief does not exist during Managing a Stage boundary process.
Should be B.
After Starting Up a Project Benefit Review Plan haven't been made. But Project Brief may need to be updated.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
WikiVicks
Highly Voted 3 years, 6 months agoManikRoy
Most Recent 1 year, 1 month agoravi_aws
1 year, 1 month agoCiluba
3 years, 11 months ago