Exam PRINCE2-Practitioner topic 12 question 3 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 3
Topic #: 12
[All PRINCE2-Practitioner Edition 6 Questions]

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Which 2 statements should be recorded under either the Records or Reporting headings?

  • A. Project Support will maintain the Risk Register.
  • B. The evaluated net effect of all risks will be updated at the end of each stage and included in the End Stage Report.
  • C. The Change Authority will report monthly to the Project Manager on the status of the change budget.
  • D. Risks that are likely to occur within the next two weeks should be recorded as imminent.
  • E. A summary of risks will be maintained and included with the monthly Highlight Reports to the Project Board.
Show Suggested Answer Hide Answer
Suggested Answer: BC 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
Statement B. The evaluated net effect of all risks will be updated at the end of each stage and included in the End Stage Report ensures that the impact of all risks, including the new threat, is assessed and reported at the end of each stage. This allows for a comprehensive review of how risks have affected the project so far and what can be expected in the next stage. Statement E. A summary of risks will be maintained and included with the monthly Highlight Reports to the Project Board ensures regular reporting of risks to the Project Board. This keeps them informed about potential issues, including the new threat, that could impact the project’s objectives.
upvoted 1 times
ravi_aws
1 year, 1 month ago
While maintaining the Risk Register (statement A) is a fundamental part of risk management, it doesn't directly address the immediate concern of assessing and reporting on the impact of the competitor's calendar release. Statements B and E focus on how to specifically handle and report on risks, which is more aligned with the immediate threat scenario described in the question.
upvoted 1 times
...
...
ameyaengg
2 years, 2 months ago
Correct Answer : B & E
upvoted 1 times
...
Alex_28
3 years, 6 months ago
I also answered B,E
upvoted 2 times
...
WikiVicks
3 years, 6 months ago
C is not a correct answer. Change is related to Issues but the question is related to Risk
upvoted 1 times
...
Ciluba
3 years, 11 months ago
Should be BE
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...