Question #: 3
Topic #: 4
[All PRINCE2-Practitioner Edition 6 Questions]

Which of the following statements would NOT be included in the Project Product Description?

  • A. Purpose of the product
  • B. Composition
  • C. Project level tolerances
  • D. Quality criteria
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
mcesarlara
4 months, 1 week ago
Selected Answer: C
The first statement is not accurate because it describes quality management in a general context rather than focusing on project-specific quality management.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
The key elements of a Project Product Description are: Purpose/business justification of the product Composition of the product and its parts Quality criteria for the product Acceptance criteria Project level tolerances relate to the overall project, not the specific product. Tolerances are defined as part of project planning and monitoring/control.
upvoted 1 times
...
ManikRoy
1 year, 2 months ago
Selected Answer: D
This one is confusing. As per A.21 appendix description of project product description, A.21.1 Purpose A.21.2 Composition A.21.5 Quality criteria. Though the composition includes mention of project level quality tolerance.
upvoted 1 times
ManikRoy
1 year, 1 month ago
I now see that the Quality criteria A.21.5 is for quality of the product itself and not as a composition. So Quality criteria is the answer as this is present in the Product description and not in the project product description, only Customers quality expectation and acceptance criteria is there.
upvoted 1 times
...
...
Carpediempyy
1 year, 2 months ago
Selected Answer: D
A.21.2 Composition The project product description includes the following: •Title •Purpose •Composition •Derivation •Customer’s quality expectations •Acceptance criteria •Project-level quality tolerances •Acceptance method Statement of the means by which acceptance will be confirmed. •Acceptance responsibilities
upvoted 2 times
...
VSLM
1 year, 3 months ago
Selected Answer: C
Project tolerances are part of Project Brief
upvoted 1 times
...
georgio1974
1 year, 3 months ago
Selected Answer: C
Ans is D quality criteria is listed on page 108, 9.3.1.2
upvoted 1 times
...
PieroBe
1 year, 4 months ago
Selected Answer: D
Quality Criteria are in the Product Descriptions not the the Project Product Description where instead we found Acceptance Criteria.
upvoted 2 times
...
WikiVicks
3 years, 6 months ago
D is the correct answer. See A.21.2 Project product description's Composition. Purpose, Composition, Project-level tolerance are all mentioned, Quality Criteria is not
upvoted 4 times
...
Ciluba
3 years, 11 months ago
About C Option 'Project Level - Quality Tolerance' should be in Project Product Description. 'Project Level Tolerance should be in Project Brief. D is not right as well. Quality criteria should be in Product Description
upvoted 3 times
...
Ciluba
3 years, 11 months ago
Should be C
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...