A is correct, 13.3: Context
The effort involved in starting up a project will vary enormously from project to project. If the project is part of a programme, the programme itself should provide the project brief and will appoint some, if not all, members of the project board, thus eliminating much of the work required in this process. In such cases, the project manager should validate what is provided by the programme and, if necessary, recommend modifications.
To solve all your queries regarding Prince2 certification, you can explore these project management Certifications courses:
https://www.knowlathon.com/project-management/prince2-agile-foundation-bangalore/
https://www.knowlathon.com/project-management/prince2-agile-certification/
Correct answer is D
Please refer 6.3.4 in page 54
If the project is part of a programme, the programme will typically define both the approach to business case development and provide an outline business case for the project.
I think C is the answer here, as per 14.5.4.4 from the Prince2 manual - the programme manager should ensure the appointment of the executive and project
manager, prepare the project brief, alert the project manager to any relevant previous lessons and ensure an
initial project management team is appointed.
The correct answer is D. Verifying the project approach and capturing previous lessons
You do not need to verify the project approach as it has been already done on the Programme level within Project Brief preparation:
https://prince2.wiki/processes/starting-up-a-project/
During this process, the project mandate will be expanded into the Project Brief. Keep in mind that the Project Brief will be used by the Project Board to decide whether to Initiate the project or not. Note: if the project is part of a program, then the program will provide most of the Project Brief. In fact, most of the work in this process will already be done by the program.
I thinkk A. is wrong. in Section 14.5.4.4 it says: "In any case, the programme manager should ensure the appointment of the executive and project manager, prepare th eproject brief,..."
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
[Removed]
Highly Voted 2 years, 6 months agoFirey
Most Recent 1 year, 4 months agoSGN63
1 year, 8 months agoknowlathon1
2 years, 11 months agoRahu
2 years, 11 months agopeppe
3 years, 1 month agoMartin77
3 years, 7 months agoWombat1987
3 years, 8 months agodemmy22
3 years, 10 months agokellysmithdec2020
3 years, 11 months agoPanzerknacker
4 years ago