To me it seems two possibilities are correct: c AND d, because among the objectives of the 'Managing a Stage Boundary' are:
'request authorization to start the next management stage'
and:
'prepare an exception plan as directed by the project board'.
BUT: the list of activities in paragraph 19.4 shows:
The activities within the managing a stage boundary process are project manager oriented and are to:
● plan the next management stage
● update the project plan
● update the business case
● report management stage end
● produce an exception plan.
(Managing Successful Projects with PRINCE2' Edition 2017.
In Manage a Stage Limit there is no authorization action, the Project Manager creates the information for the Project Board that authorizes in Directing a Project
Option C is correct, while authorization for the stage plan take place in the directing a project process.
upvoted 7 times
...
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
daaniel
Highly Voted 3 years, 2 months agoTaiH
Most Recent 6 months agoRisto83
1 year, 6 months agoMichelleVD
2 years, 4 months agopeppe
2 years, 9 months agoJasonbahr
3 years, 3 months agoFarbod
3 years, 4 months agodemmy22
3 years, 6 months agoTatina1
3 years, 8 months agoPreeti444
3 years, 9 months agoMehan
3 years, 6 months ago