Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 138 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 138
Topic #: 1
[All PRINCE2-Foundation Questions]

Which activity takes place within the Managing a Stage Boundary process?

  • A. Produce Highlight Reports
  • B. Take corrective action within the limits of a stage's tolerance
  • C. Produce an Exception Plan
  • D. Authorize a Stage Plan for the next stage
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
daaniel
Highly Voted 3 years, 6 months ago
To me it seems two possibilities are correct: c AND d, because among the objectives of the 'Managing a Stage Boundary' are: 'request authorization to start the next management stage' and: 'prepare an exception plan as directed by the project board'. BUT: the list of activities in paragraph 19.4 shows: The activities within the managing a stage boundary process are project manager oriented and are to: ● plan the next management stage ● update the project plan ● update the business case ● report management stage end ● produce an exception plan. (Managing Successful Projects with PRINCE2' Edition 2017.
upvoted 5 times
...
TaiH
Most Recent 10 months, 2 weeks ago
Selected Answer: C
I think C is correct as well. D is directing project.
upvoted 1 times
...
Risto83
1 year, 11 months ago
C is correct. "Authorization" is done at Directing a project (DP).
upvoted 2 times
...
MichelleVD
2 years, 9 months ago
Selected Answer: C
D is directing a project.
upvoted 3 times
...
peppe
3 years, 1 month ago
C is correct
upvoted 3 times
...
Jasonbahr
3 years, 7 months ago
Tricky, but I concur with C
upvoted 2 times
...
Farbod
3 years, 9 months ago
C is correct, The exception plan is prepared in SB and submitted to the Project Board for approval in the same way as a stage plan.
upvoted 3 times
...
demmy22
3 years, 10 months ago
this is confusing, I thought it was option D
upvoted 1 times
...
Tatina1
4 years, 1 month ago
In Manage a Stage Limit there is no authorization action, the Project Manager creates the information for the Project Board that authorizes in Directing a Project
upvoted 3 times
...
Preeti444
4 years, 1 month ago
option C can take place where as option D is a definite activity
upvoted 3 times
Mehan
3 years, 10 months ago
Option C is correct, while authorization for the stage plan take place in the directing a project process.
upvoted 7 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...