Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 201 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 201
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is a minimum requirement for applying the change theme?

  • A. To establish a change budget to fund changes in scope
  • B. To appoint the project manager as part of the change authority
  • C. To define the project's approach to baselining products
  • D. To record every issue that is raised in the issue register
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Reference:
http://prince2.wiki/Themes#Change_Theme

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
sohrabiani
Highly Voted 4 years, 1 month ago
I think not all Issues need to be registered in issue register. and some of them can be registered in the daily log
upvoted 5 times
Mehan
3 years, 10 months ago
and option D says, only those issues, which raised to the issue register. so D is correct.
upvoted 1 times
...
...
Examcollectorthanos
Most Recent 2 weeks ago
C: Baseline for Control: A baseline is a snapshot of a product or set of products at a specific point in time. It acts as an agreed-upon reference point. Defining how baselines are created and managed is crucial for controlling change. Without a baseline, it's impossible to assess the impact of a proposed change or to track deviation
upvoted 1 times
...
bes_i
4 months, 1 week ago
Selected Answer: C
c looks correct
upvoted 1 times
...
Fay_T
1 year, 8 months ago
Issues do not need to be recorded in the issue register if they have been sufficiently covered in the issue report. The answer is C .
upvoted 1 times
...
MrMooMooBee
1 year, 9 months ago
I think both are correct: C: The project (under the Change theme) should define how product baselines are created, maintained and controlled. D: Ensure that issues are captured, examined, managed and reviewed throughout the project
upvoted 1 times
...
peppe
3 years, 1 month ago
". To define the project's approach " is not correct i believe
upvoted 1 times
...
consta
3 years, 4 months ago
C is the correct answer. It cannot be D because only the formal issues are recorded in the issue register. The informal, are registered in the daily log.
upvoted 3 times
...
theotenis
3 years, 6 months ago
C and D are correct according to the PRINCE2 manual, section 11.2: • define how product baselines are created, maintained and controlled • maintain some form of issue register to record identified issues and decisions relating to their analysis, management and review • ensure that project issues are captured, examined, managed and reviewed throughout the project lifecycle
upvoted 1 times
...
Wombat1987
3 years, 7 months ago
D is the right answer. https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes#theme-6 Minimum requirements You must define a risk management approach covering the risk management procedure to be used, and the roles and responsibilities for risk management. You must maintain some form of risk register to record and manage risks and must ensure that risks are identified, assessed, managed and reviewed throughout the project. You must use lessons to inform risk identification and management.
upvoted 1 times
...
Farbod
3 years, 9 months ago
C is correct, "Define how product baselines are created, maintained and controlled"
upvoted 3 times
...
Tommaso
3 years, 10 months ago
C is correct. D says to maintain the issue register, not to record every issue there. B is incorrect too, as the change authority does not have to be the PM
upvoted 4 times
...
Panzerknacker
4 years ago
B seems to be correct. As stated in section 11.2: "define how product baselines are created, maintained and controlled"
upvoted 1 times
Panzerknacker
4 years ago
But D is also correct as it says "maintain some form of issue register to record identified issues and decisions ..."
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...