The correct answer is:
C. To define the project's approach to baselining products
Explanation:
The Change Theme in PRINCE2 (Projects IN Controlled Environments) is about managing changes to the project’s baseline products and ensuring that any changes are controlled. A minimum requirement of the Change Theme is to define how products will be baselined, as this establishes a foundation for managing changes.
Key points:
Baselining involves creating a reference point for products so any changes can be tracked against the original version.
Without baselining, it would be impossible to assess the impact of proposed changes.
C: Baseline for Control: A baseline is a snapshot of a product or set of products at a specific point in time. It acts as an agreed-upon reference point. Defining how baselines are created and managed is crucial for controlling change. Without a baseline, it's impossible to assess the impact of a proposed change or to track deviation
I think both are correct:
C: The project (under the Change theme) should define how product baselines are created, maintained and controlled.
D: Ensure that issues are captured, examined, managed and reviewed throughout the project
C is the correct answer.
It cannot be D because only the formal issues are recorded in the issue register. The informal, are registered in the daily log.
C and D are correct according to the PRINCE2 manual, section 11.2:
• define how product baselines are created, maintained and controlled
• maintain some form of issue register to record identified issues and decisions relating to their analysis, management and review
• ensure that project issues are captured, examined, managed and reviewed throughout the project lifecycle
D is the right answer.
https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes#theme-6
Minimum requirements
You must define a risk management approach covering the risk management procedure to be used, and the roles and responsibilities for risk management. You must maintain some form of risk register to record and manage risks and must ensure that risks are identified, assessed, managed and reviewed throughout the project. You must use lessons to inform risk identification and management.
C is correct. D says to maintain the issue register, not to record every issue there. B is incorrect too, as the change authority does not have to be the PM
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
sohrabiani
Highly Voted 4 years, 6 months agoMehan
4 years, 3 months agoselimbeyhan
Most Recent 2 months, 2 weeks agoExamcollectorthanos
5 months, 1 week agobes_i
9 months agoFay_T
2 years, 1 month agoMrMooMooBee
2 years, 2 months agopeppe
3 years, 6 months agoconsta
3 years, 9 months agotheotenis
3 years, 11 months agoWombat1987
4 years agoFarbod
4 years, 1 month agoTommaso
4 years, 3 months agoPanzerknacker
4 years, 5 months agoPanzerknacker
4 years, 5 months ago