Exam PRINCE2-Practitioner topic 1 question 8 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 8
Topic #: 1
[All PRINCE2-Practitioner Edition 6 Questions]

The executive has asked the project manager to plan for the 'e-learning course' to be used as soon as it is accredited. The aim is to start selling the 'e-learning course' while the remainder of the outputs relating to classroom-based delivery are finished. The sales of the 'e-learning course' will be entered into the business case.
Why is the executive's decision to deliver the benefits early appropriate for managing the business case?

  • A. Because organizations with mature project management often include the early justification for the project in the business case.
  • B. Because the outputs being delivered incrementally will be beneficial and will allow the business case to be justified.
  • C. Because one of the PRINCE2 principles is that a project should focus on products to deliver the outputs early.
  • D. Because the business case should be updated after every increment of the 'e-learning course'.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Hazemsh
Highly Voted 3 years, 11 months ago
correct answer is B ( check 6.3.1)
upvoted 6 times
...
mcesarlara
Most Recent 4 months, 1 week ago
Selected Answer: B
Delivering benefits early through the incremental delivery of outputs, such as starting to sell the 'e-learning course' as soon as it is accredited, can provide early returns and validate the business case. This approach allows the project to demonstrate value sooner and supports ongoing justification for the project, ensuring that the business case remains robust and aligned with business objectives. While focusing on products is a PRINCE2 principle, the key reason here is the incremental delivery of beneficial outputs and their impact on the business case.
upvoted 1 times
...
ManikRoy
11 months, 2 weeks ago
Selected Answer: B
B. Because the outputs being delivered incrementally will be beneficial and will allow the business case to be justified.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
Correct answer is B
upvoted 1 times
...
PieroBe
1 year, 4 months ago
Agree with all of you, it is B
upvoted 1 times
...
Samuel77
1 year, 7 months ago
Correct answer is B
upvoted 1 times
...
KPBGBAP
1 year, 9 months ago
Selected Answer: B
Correct Answer is B ( straight forward)
upvoted 1 times
...
ameyaengg
2 years, 2 months ago
Correct Answer is B ( straight forward)
upvoted 2 times
...
lovelifeysl_2021
3 years ago
I think it is B
upvoted 2 times
...
Pauly
4 years, 2 months ago
Topic 12 is a dump of 202 questions. In the first questions I'm missing background 'scenario' information.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...