Exam PRINCE2-Foundation topic 1 question 263 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 263
Topic #: 1
[All PRINCE2-Foundation Questions]

Which principle helps to ensure that all changes to the outputs are agreed?

  • A. Defined roles and responsibilities
  • B. Focus on products
  • C. Learn from experience
  • D. Manage by exception
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Constanza
Highly Voted 3 years, 10 months ago
B is correct, p.26/3.6
upvoted 6 times
...
Examcollectorthanos
Most Recent 2 weeks, 2 days ago
Answer = B. A. Defined roles and responsibilities: Clarifies who is responsible for various aspects of the project, but not the specific process of agreeing on changes.   C. Learn from experience: Encourages using past experiences to improve the project, but doesn't directly address change control.   D. Manage by exception: Focuses on delegating authority and escalating issues, but doesn't ensure agreement on output changes.
upvoted 1 times
...
fgtfgtet4r56y
1 year, 1 month ago
B. Focus on products The principle of "Focus on products" in PRINCE2 helps ensure that all changes to the project's outputs (products) are agreed upon. It emphasizes the importance of clearly defining and understanding the project's products (deliverables) and their quality criteria. When changes are proposed, they need to align with the agreed-upon product descriptions and quality requirements, and this principle helps ensure that changes are properly assessed and agreed upon.
upvoted 3 times
...
lferolm
1 year, 9 months ago
Selected Answer: B
B is correct
upvoted 1 times
...
KopytinaN
4 years, 2 months ago
B is correct
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...