Option D is correct. As per Prince2 Manual section 12.2
review the business justification when exceptions are raised (PRINCE2's continued business
justification principle)
The correct answer is: B. Throughout each stage
Explanation:
According to PRINCE2, one of the minimum requirements for applying the Progress theme is to:
Review the Business Justification throughout the project, typically at the end of each stage (during stage boundary assessments).
This ensures that the project continues to be viable, desirable, and achievable — the core principles of a valid Business Case.
The correct answer is: B. Throughout each stage
In PRINCE2, the progress theme ensures the project remains viable and aligned with its business justification. The business justification must be reviewed throughout each stage to confirm that the project remains desirable, viable, and achievable. This continuous review helps assess whether the project's benefits outweigh its costs and risks.
D is correct- if 'minimum' was not worded B would be correct; B. Throughout each stage: Reviews at stage boundaries are important, but the minimum requirement is to review when exceptions occur.
I was confused at first but the correct answer is D.
https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes#theme-7
Minimum requirements
You must define your project's approach to controlling progress in the project initiation documentation (PID). You must manage by stages, set tolerances and manage by exception against these tolerances. You must review the business justification when exceptions are raised and learn lessons throughout the project.
To meet the minimum requirements for applying the progress theme - this is the key to this tricky question. 12.2 in the prince manual states (review the business justification when exceptions are raised (PRINCE2's continued business
justification principle) ) so D is the correct answer.
I was confused at first but the correct answer is D.
https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes#theme-7
Minimum requirements
You must define your project's approach to controlling progress in the project initiation documentation (PID). You must manage by stages, set tolerances and manage by exception against these tolerances. You must review the business justification when exceptions are raised and learn lessons throughout the project.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
GetRaj
Highly Voted 4 years, 10 months agoMehan
4 years, 5 months agoKjennset
Most Recent 2 months agoselimbeyhan
5 months, 1 week agoExamcollectorthanos
7 months, 4 weeks agoExamcollectorthanos
8 months agoTesteurtest
1 year, 10 months agoRD27
1 year, 12 months agorenza
2 years, 4 months agopeppe
3 years, 8 months agoMartin77
4 years, 2 months agoWombat1987
4 years, 3 months agoFarbod
4 years, 4 months agoTommaso
4 years, 5 months agoAgnesM
4 years, 8 months agosohrabiani
4 years, 9 months agoMaximeHU
4 years, 10 months ago