Exam PRINCE2-Foundation topic 1 question 206 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 206
Topic #: 1
[All PRINCE2-Foundation Questions]

Which describes an off-specification?

  • A. An interdependency between products that was previously unidentified
  • B. The addition of an improvement to a product description
  • C. A prototype demonstrating a possible design solution
  • D. The production of more than the defined quantity of a specialist product
  • E. That the right people are involved in appropriate roles
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
https://www.prince2primer.com/prince2-change-control/

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
D. The production of more than the defined quantity of a specialist product. Here's why: Off-specification in PRINCE2 refers to a situation where a product does not meet its defined requirements or acceptance criteria. This includes producing the wrong quantity, even if it's more than expected. While it might seem like having "more" is a good thing, it can lead to:
upvoted 1 times
...
Examcollectorthanos
2 weeks, 2 days ago
Choose D, but could be A asweel.
upvoted 1 times
...
bes_i
4 months ago
Selected Answer: D
D. The production of more than the defined quantity of a specialist product In PRINCE2, an off-specification refers to a situation where a product or deliverable deviates from its specified requirements or quality criteria. This includes cases where more (or fewer) products are produced than what was originally defined or where the products do not meet the agreed-upon standards.
upvoted 1 times
...
Nugi
3 years, 4 months ago
How many correct answer? If two answers, it seems like D and A.
upvoted 2 times
...
Martin77
3 years, 7 months ago
A.9.2 (Prince2 guide) Off-specifications Listing any missing products or products that do not meet the original requirements, and confirmation of any concessions granted
upvoted 2 times
...
DS001
3 years, 7 months ago
Off-specification doesn't talk about 'interdependency between products'
upvoted 1 times
...
Mehan
3 years, 10 months ago
I think A is correct
upvoted 2 times
...
sohrabiani
4 years, 1 month ago
I thin both A & D are correct since the producing the product more than required number also can be categorized as Off-Specification
upvoted 1 times
...
Petza
4 years, 3 months ago
According to A.8.2 Composition, where mentioned about Off-specifications: "Listing any missing products or products that do not meet the original requirements, and confirmation of any concessions granted" in a glossary also given a description for off-specification - Something that should be provided by the project, but currently is not (or is forecast not to be) . It might be a missing product or a product not meeting its specifications. It looks A is a correct answer
upvoted 4 times
...
GetRaj
4 years, 3 months ago
Option D seems to be correct.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...