D. The production of more than the defined quantity of a specialist product.
Here's why:
Off-specification in PRINCE2 refers to a situation where a product does not meet its defined requirements or acceptance criteria. This includes producing the wrong quantity, even if it's more than expected. While it might seem like having "more" is a good thing, it can lead to:
D. The production of more than the defined quantity of a specialist product
In PRINCE2, an off-specification refers to a situation where a product or deliverable deviates from its specified requirements or quality criteria. This includes cases where more (or fewer) products are produced than what was originally defined or where the products do not meet the agreed-upon standards.
A.9.2 (Prince2 guide) Off-specifications Listing any missing products or products that do not meet the original requirements,
and confirmation of any concessions granted
According to A.8.2 Composition, where mentioned about Off-specifications: "Listing any missing products or products that do not meet the original requirements, and confirmation of any concessions granted"
in a glossary also given a description for off-specification - Something that should be provided by the project, but currently is not (or is forecast not to be) . It might be a missing product or a product not meeting its specifications.
It looks A is a correct answer
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
2 weeks agoExamcollectorthanos
2 weeks, 2 days agobes_i
4 months agoNugi
3 years, 4 months agoMartin77
3 years, 7 months agoDS001
3 years, 7 months agoMehan
3 years, 10 months agosohrabiani
4 years, 1 month agoPetza
4 years, 3 months agoGetRaj
4 years, 3 months ago