Question #: 151
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is a key decision made during the 'directing a project' process?

  • A. Select and appoint the project executive
  • B. Approve the project manager role description
  • C. Confirm that the benefits management approach addresses all expected benefits
  • D. Approve the proposed project mandate
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
GetRaj
Highly Voted 4 years, 3 months ago
Option C is correct as per Prince2 Manual section 15. 4. 2 Authorize the project Review and approve the benefits management approach. Confirm it addresses all the expected benefits and meets the needs of corporate, programme management or the customer. is an activity as pert of Authorize the project which happens as part of "Directing a Project" process
upvoted 17 times
...
AgnesM
Highly Voted 4 years ago
Project Manager role description is approved by Corporate or Program Managment in "Starting up a project" process, therefore option B is not correct answer to this question. "Directing a project" process consist of authorising the project, where Benefits managment approach is being approved by project board and corporate and programme managment, therefore answer C is CORRECT to this question.
upvoted 10 times
...
renza
Most Recent 1 year, 9 months ago
Selected Answer: C
Answer is (C) Confirm that the benefits management approach addresses all expected benefits Per Prince2 Manual section 15. 4. 2 Authorize the project Review and approve the benefits management approach. Confirm it addresses all the expected benefits and meets the needs of corporate, programme management or the customer. is an activity as part of Authorize the project which happens as part of "Directing a Project" process. Project Manager role description is approved by Corporate or Program Managment in "Starting up a project" process, therefore option B is not correct answer.
upvoted 2 times
...
Chucky2
1 year, 12 months ago
Selected Answer: C
C is correct
upvoted 1 times
...
jj0097
2 years, 4 months ago
Selected Answer: C
C is correct
upvoted 1 times
...
natavorc
2 years, 5 months ago
should correct from B to C
upvoted 1 times
...
peppe
3 years, 1 month ago
C is correct
upvoted 2 times
...
PMBT_1017
3 years, 6 months ago
Option C is correct.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...