Option C is correct as per Prince2 Manual section 15. 4. 2 Authorize the project
Review and approve the benefits management approach. Confirm it addresses all the expected benefits and
meets the needs of corporate, programme management or the customer.
is an activity as pert of Authorize the project which happens as part of "Directing a Project" process
Project Manager role description is approved by Corporate or Program Managment in "Starting up a project" process, therefore option B is not correct answer to this question.
"Directing a project" process consist of authorising the project, where Benefits managment approach is being approved by project board and corporate and programme managment, therefore answer C is CORRECT to this question.
Answer is (C) Confirm that the benefits management approach addresses all expected benefits
Per Prince2 Manual section 15. 4. 2 Authorize the project Review and approve the benefits management approach. Confirm it addresses all the expected benefits and meets the needs of corporate, programme management or the customer. is an activity as part of Authorize the project which happens as part of "Directing a Project" process.
Project Manager role description is approved by Corporate or Program Managment in "Starting up a project" process, therefore option B is not correct answer.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
GetRaj
Highly Voted 4 years, 3 months agoAgnesM
Highly Voted 4 years agorenza
Most Recent 1 year, 9 months agoChucky2
1 year, 12 months agojj0097
2 years, 4 months agonatavorc
2 years, 5 months agopeppe
3 years, 1 month agoPMBT_1017
3 years, 6 months ago