Question #: 6
Topic #: 1
[All PRINCE2-Practitioner Edition 6 Questions]

Which of the following activities is the Executive responsible for?

  • A. Ensure the desired outcome of the project is specified
  • B. Responsible for the benefits review plan
  • C. Assess and update the Business Case at the end of each stage
  • D. Responsible for the Benefits Review Plan post project
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
B. Responsible for the benefits review plan The page states that the Executive is responsible for "Ensuring that the project delivers the projected business benefits." This aligns with being responsible for the benefits review plan, which outlines how the benefits will be reviewed and measured after project completion. The other options are responsibilities of the Project Board or Project Manager, not the Executive specifically. The Executive ensures the desired outcome is specified by authorizing project startup, but is not directly responsible for specifying the outcome itself. Assessing and updating the Business Case is a Project Board duty. The Project Manager is responsible for the Benefits Review Plan during the project, while the Executive handles it post-project. So in summary, the Executive's unique responsibility listed in the options is oversight of the Benefits Review Plan after the project finishes.
upvoted 1 times
...
WikiVicks
3 years, 6 months ago
Correct, Executive. 6.2.3 says "By default, the executive is responsible for ensuring that benefits reviews are planned and executed, but there are circumstances where this may not always be the case
upvoted 4 times
...
Alex_28
3 years, 7 months ago
correct, only Executive p.52
upvoted 2 times
...
Jimeth
4 years, 3 months ago
correct 6.2.3
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...