Question #: 6
Topic #: 8
[All PRINCE2-Practitioner Edition 6 Questions]

Who is responsible for confirming stage and project progress against agreed tolerances?

  • A. Project Support
  • B. Executive
  • C. Project Assurance
  • D. Project Manager
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Rssahota
Highly Voted 4 years, 3 months ago
table 12.2
upvoted 7 times
...
SantiagoAregentina
Most Recent 1 year, 2 months ago
Selected Answer: C
Ref Table 12.2
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...