Which of the following risk responses can be used for either an opportunity or a threat?

  • A. Reduce
  • B. Share
  • C. Reject
  • D. Enhance
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Rssahota
Highly Voted 4 years, 3 months ago
RINCE2 suggest 6 responses for threats and four responses for opportunities. The 6 responses for threats are: Avoid, Reduce, Fallback, Transfer, Share and Accept The 4 responses for Opportunity are Exploit, Enhance, Share and Reject.
upvoted 6 times
...
Stu_Dent
Most Recent 7 months, 2 weeks ago
B is correct. Ref: Table 10.3 (page 132)
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
The risk responses are: A) Reduce - Applies to threats, aims to reduce probability or impact B) Share - Can apply to both opportunities and threats, involves sharing risk to reduce exposure C) Reject - Usually used for threats, avoiding the risk by eliminating the cause D) Enhance - Applies to opportunities, aims to increase probability or impact So out of the options, Share is the risk response that can be utilized for both opportunities and threats.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...