A. To identify whether an issue affects the continuation of the project.
Here's why:
Issue and Change Control: The change theme provides a structured approach to managing issues and changes throughout the project. A fundamental aspect of this is determining the impact of an issue.
Definitely A.
Reference: To be following PRINCE2, a project must, as a minimum:
● define its change control approach. This approach must minimally cover:
● how issues are identified and managed
● assessing whether identified issues might have a material impact on the business justification of the project (PRINCE2’s continued business justification principle)
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
2 weeks, 2 days agocostin31
8 months, 1 week agoNugi
3 years, 4 months agoMehan
3 years, 10 months agoMehan
3 years, 10 months agoJimeth
4 years, 3 months agoKiana
4 years, 3 months ago