Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 52 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 52
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

  • A. Those with a financial interest in the project
  • B. Those who will manage the project on a day-to-day basis
  • C. Those who will specify the desired outputs of the project
  • D. Those who will create the project's outputs
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Farbod
Highly Voted 3 years, 9 months ago
B is Project manager, but it is correct answer There are three primary stakeholders, which are: • Business sponsors: who endorse the objectives and ensure the project provides value for money. • Users: who will be using the products to generate benefits, usually after the project is completed. • Suppliers: who provide the resources and expertise needed to undertake the project work and these can be internal or external
upvoted 7 times
...
Firey
Most Recent 1 year, 4 months ago
There are three primary stakeholders in any PRINCE2 project: the business sponsor, the users, and the suppliers. Each of these stakeholders has specific roles and responsibilities that must be fulfilled in order for the project to be successful.
upvoted 1 times
...
renza
1 year, 9 months ago
Selected Answer: B
PRINCE2 identifies three principal categories of project stakeholders (business, user and supplier) managing day-to-day basis is the PM role
upvoted 1 times
...
Ajs25
1 year, 12 months ago
I would have thought D
upvoted 1 times
...
Jasonbahr
3 years, 7 months ago
I concur with B
upvoted 2 times
...
Seagun
4 years, 4 months ago
Is B not what the Project manager does?
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...