Question #: 188
Topic #: 1
[All PRINCE2-Foundation Questions]

According to PRINCE2, why might there be more than one business case for a project?

  • A. There may be more than one management stage in the project
  • B. The project may be in a commercial environment with a number of suppliers
  • C. There may be more than one work package being delivered in the project
  • D. The project may be in a programme environment
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://www.prince2primer.com/prince2-practitioner-questions-answers-business-case/

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Tatina1
Highly Voted 4 years, 1 month ago
I think it's B, because even though the project could be part of a program, that project only has a customer business justification, but each supplier could have their own business justification.
upvoted 6 times
Mehan
3 years, 10 months ago
Agree B is correct
upvoted 2 times
...
...
SGN63
Most Recent 1 year, 8 months ago
Selected Answer: B
It's B
upvoted 1 times
...
peppe
3 years, 1 month ago
B is the most correct
upvoted 1 times
...
Nugi
3 years, 4 months ago
Correct answer is B. Reference: 6.3.3 Customers and suppliers will usually need their own business cases.
upvoted 1 times
...
Martin77
3 years, 7 months ago
B seems like the logical answer. Reference Prince2 manual - 6.3.3
upvoted 1 times
...
christinelucas
3 years, 7 months ago
The Agile Foundation certification exam consists of a closed-book multiple-choice paper with a score of 50% required to pass the Agile Foundation exam. After passing your Agile Foundation exam you will have earned your official Agile Foundation certification and can then proceed to the <a herf="https://www.novelvista.com/prince2-agile-practitioner">prince2 agile training</a> course if you wish to further your studies. RINCE2 Agile Foundation is for individuals who are new to PRINCE2 and are working in or around an agile project environment. It aims to cover overview of PRINCE2, an introduction to agile and how to apply the two together.
upvoted 2 times
...
Jasonbahr
3 years, 7 months ago
According to this quote from the handbook "The business case for a customer's project is separate from a supplier's business case for bidding for and working on that customer's project. The customer needs to ensure that its project is viable and risks are acceptable, bearing in mind the suppliers chosen. A supplier would have to ensure that it will benefit from the work it undertakes on the project. In other words, the project will be profitable from the supplier's perspective." I would concur with B
upvoted 2 times
...
GLKTYI
4 years, 4 months ago
It should be D. Program organized multiple project to achieve organization strategic objective, each project has it’s own specific objective which can involved multiple vendor to deliver the project output.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...