Question #: 164
Topic #: 1
[All PRINCE2-Foundation Questions]

To meet the minimum requirements for applying the progress theme, what must be considered?

  • A. How lessons will be learned
  • B. How time-driven reports will be produced
  • C. Which management products will be baselined
  • D. Who is responsible for reporting on progress
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
GLKTYI
Highly Voted 4 years, 4 months ago
Reporting frequency is not minimum requirement, in simple project checkpoint can be verbal. lesson learned is considered minimum requirement.
upvoted 7 times
...
AgnesM
Highly Voted 4 years ago
Answer A is correct according to paragraph 12.2 of Prince2 manual.
upvoted 7 times
...
Kristyna
Most Recent 1 year, 1 month ago
I agree with answer B as "How time-driven reports will be produced " is part of approach to controlling progress as in 12.2 defined
upvoted 1 times
...
Haranp12
1 year, 1 month ago
I agree with the other comments that the answer should be A
upvoted 1 times
...
Testeurtest
1 year, 3 months ago
Selected Answer: A
To be following PRINCE2, a project must, as a minimum: ● define its approach to controlling progress in the PID ● be managed by stages (PRINCE2’s manage by stages principle) ● set tolerances and be managed by exception against these tolerances (PRINCE2’s manage by exception principle) ● review the business justification when exceptions are raised (PRINCE2’s continued business justification principle) ● learn lessons (PRINCE2’s learn from experience principle).
upvoted 2 times
...
SGN63
1 year, 8 months ago
Selected Answer: A
a is correct
upvoted 1 times
...
renza
1 year, 9 months ago
Selected Answer: A
a is correct
upvoted 1 times
...
Risto83
1 year, 11 months ago
A 12.2: To be following PRINCE2, a project must, as a minimum: ● define its approach to controlling progress in the PID ● be managed by stages (PRINCE2’s manage by stages principle) ● set tolerances and be managed by exception against these tolerances (PRINCE2’s manage by exception principle) ● review the business justification when exceptions are raised (PRINCE2’s continued business justification principle) ● learn lessons (PRINCE2’s learn from experience principle).
upvoted 2 times
...
King_Laps
2 years ago
Answer A is correct
upvoted 1 times
...
peppe
3 years, 1 month ago
A is correct 12.2
upvoted 1 times
...
Martin77
3 years, 7 months ago
A is correct, according to 12.2 section of the Prince2 manual
upvoted 2 times
...
Tommaso
3 years, 10 months ago
D seems to be correct
upvoted 2 times
Tommaso
3 years, 10 months ago
I meant A seems to be correct
upvoted 3 times
...
...
Petza
4 years, 3 months ago
PRINCE2 manual paragraph 12.2
upvoted 4 times
Mehan
3 years, 10 months ago
I agree with this, according to Ref.12.2
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...