One of the key activities in the Controlling a Stage process is to review the status of the work packages . Work packages are the smallest units of work in PRINCE2, and they are assigned to team members to complete. By reviewing the status of the work packages, the project manager can gather information on the actual progress made and update the stage plan accordingly.
A is wrong by default as its missing the word "Management"
B is correct "update"
Review the management stage status "reviews", but I dont think it "updates"
update stage plan, is part of the review the management stage status, pg 223 fig 17.5
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
ManikRoy
1 year, 1 month agoravi_aws
1 year, 1 month agoPieroBe
1 year, 4 months agoMortenC
1 year, 9 months agoMEHREEN1985
1 year, 12 months agoMEHREEN1985
1 year, 8 months agotimedout
3 years, 2 months agoxayay74894
3 years, 3 months agoxayay74894
3 years, 3 months agoCiluba
3 years, 11 months agojohnzoids
4 years, 4 months agojohnzoids
4 years, 4 months ago