Exam PRINCE2-Practitioner topic 13 question 5 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 5
Topic #: 13
[All PRINCE2-Practitioner Edition 6 Questions]

What additional risk will this place on the project?

  • A. None because risks associated with the centralization and rationalization of the Facilities Division will be managed by another project.
  • B. These changes will delay stage 3 by three weeks.
  • C. There is only ֲ£70k left in the project change budget.
  • D. The reduced value of the contracted services required by the Outsourcing project may result in an insufficient number of proposals being received.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
pollon
3 years, 3 months ago
Answer is D
upvoted 1 times
...
pollon
3 years, 3 months ago
The question should be "If the decision to remove Facilities services from the scope of the Restructuring project, what risk will this introduce to the project?"
upvoted 2 times
...
Petza
4 years, 2 months ago
According to the book "PRINCE2 Foundation Exam Practice Questions & Dumps: 150+ Exam", correct answer is A, section change theme explanation
upvoted 1 times
...
johnzoids
4 years, 4 months ago
there is no answer given
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...