According to PRINCE2, which statement about the Configuration Management Strategy for the Outsourcing project is correct?
A.
Every project needs a Configuration Management Strategy, even if the organization has existing configuration management standards, because every project has different circumstances.
B.
A separate Configuration Management Strategy will be required for each of the suppliers within this project because each will have a different way of managing and storing products.
C.
A Configuration Management Strategy is unnecessary for this project because the MFH document control process is documented. It is acceptable simply to reference this in the Quality Management Strategy.
A. Every project needs a Configuration Management Strategy, even if the organization has existing configuration management standards, because every project has different circumstances.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
johnzoids
Highly Voted 4 years, 4 months agoravi_aws