In which Management product would the Project Board specify where the authority for change requests lies?

  • A. Risk Management Strategy
  • B. Quality Management Strategy
  • C. Communication Strategy
  • D. Configuration Management Strategy
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
PieroBe
1 year, 4 months ago
Selected Answer: D
With the new syllabus this product is named Change Control Approach; in this product is reported whether a change authority is engaged in the project (ref A.3).
upvoted 2 times
...
PrincessOfHess
1 year, 10 months ago
D (A 6.1)
upvoted 2 times
...
matters
3 years, 1 month ago
Using the 6th edition manual, the Change Control Approach is the answer
upvoted 2 times
KANDUUR
2 years, 9 months ago
A.3.1.
upvoted 1 times
...
...
johnzoids
4 years, 4 months ago
This is part of the old syllabus, 2009 edition. in the 2017 or 6th edition there are no things as strategy but approaches.
upvoted 3 times
Rssahota
4 years, 3 months ago
Does this also apply for the following question too?
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...