C is correct:
The team manager ensures that products are created and delivered by the team to the project by:
● accepting and checking authorized work packages from the project manager
● ensuring that interfaces identified in the work package are maintained
● creating a team plan for the work packages being assigned (this may be done in parallel with the project
manager creating the stage plan for the management stage)
● ensuring that the products are developed in accordance with any development method(s) specified in the
work package
● demonstrating that each product meets its quality criteria through the quality method(s) specified in the
product description; this may include using the PRINCE2 quality review technique (see Chapter 8)
● obtaining approval for completed products from the authorities identified in the product description
● delivering the products to the project manager in accordance with any procedures specified in the work package.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Martin77
Highly Voted 3 years, 7 months ago[Removed]
Most Recent 2 years, 6 months agopeppe
3 years, 1 month agoJasonbahr
3 years, 7 months agoJimeth
4 years, 3 months agoejaymac
4 years, 4 months ago