Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 257 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 257
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is a minimum requirement when applying the business case theme?

  • A. To specify the solution to be used to deliver the business option selected
  • B. To ensure the corporate business plan is updated with the project costs and benefits
  • C. To define the management actions required to ensure the project's outcomes are achieved
  • D. To integrate the benefits management approach with the project and stage plans
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
C; Why the other options are not the minimum requirement: A. To specify the solution to be used to deliver the business option selected: While important, this is more related to the project's solution and design, not the core of the Business Case theme. B. To ensure the corporate business plan is updated with the project costs and benefits: This is good practice for alignment, but not the absolute minimum requirement for the Business Case theme itself. D. To integrate the benefits management approach with the project and stage plans: This is important for benefits realization, but the minimum requirement focuses on defining the management actions. Key takeaway: The Business Case theme in PRINCE2 requires a proactive approach to achieving outcomes and realizing benefits. Defining the necessary management actions is crucial for ensuring the project delivers true value to the organization.
upvoted 1 times
...
Toyeeb
7 months ago
Selected Answer: C
C is correct, check the manual.
upvoted 2 times
...
King_Laps
2 years, 1 month ago
The answer is C
upvoted 1 times
...
Martin77
3 years, 7 months ago
C is correct, reference Prince2 guide 6.2 define the management actions that will be put in place to ensure that the project's outcomes are achieved and confirm that the project's benefits are realized (PRINCE2's continued business justification principle)
upvoted 3 times
...
Wombat1987
3 years, 7 months ago
C is the correct answer. https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes Minimum requirements Your project must create and maintain a business justification (in the form of a business case), and you should review and update it throughout your project. You must define management actions to ensure the expected outcomes are achieved and the benefits are realized. You must define and document the roles and responsibilities for the business case and the management of benefits. Finally, you must produce and maintain a benefits management approach.
upvoted 2 times
...
Lenlenlen
4 years, 4 months ago
it should be C
upvoted 2 times
...
Lenlenlen
4 years, 4 months ago
agreed, it should be C
upvoted 1 times
...
ejaymac
4 years, 4 months ago
This answer should be C
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...