Exam PRINCE2-Foundation topic 1 question 162 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 162
Topic #: 1
[All PRINCE2-Foundation Questions]

Which process is used to define how baselines will be established and controlled?

  • A. Controlling a stage
  • B. Directing a project
  • C. Initiating a project
  • D. Starting up a project
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
GetRaj
Highly Voted 4 years, 4 months ago
Option C seems to be correct
upvoted 7 times
...
GLKTYI
Highly Voted 4 years, 4 months ago
It should be C, starting up project not defining baseline but define and confirm initial scope in project brieft
upvoted 7 times
...
Testeurtest
Most Recent 1 year, 3 months ago
Selected Answer: C
Starting up is about defining what customer needs, Init the project is about defining how it will be done and provide documents https://prince2.wiki/processes/initiating-a-project/
upvoted 2 times
...
SGN63
1 year, 8 months ago
Selected Answer: C
C is the correct answer
upvoted 1 times
...
Anapellicer
1 year, 8 months ago
Selected Answer: C
C should be the correct answer
upvoted 1 times
...
renza
1 year, 9 months ago
Selected Answer: C
c is the correct answer
upvoted 1 times
...
Risto83
1 year, 11 months ago
C 16.2: The objective of the initiating a project process is to ensure that there is a common understanding of: ● the reasons for doing the project, the benefits expected and the associated risks ● the scope of what is to be done and the products to be delivered ● how and when the project’s products will be delivered and at what cost ● who is to be involved in the project decision-making ● how the quality required will be achieved ● how baselines will be established and controlled ● how risks, issues and changes will be identified, assessed and controlled ● how progress will be monitored and controlled ● who needs information, in what format and at what time ● how the corporate, programme management or customer method will be tailored to suit the project.
upvoted 6 times
...
Trikuta_Kaira
2 years, 5 months ago
Answer should be "C" (Initiating a Project) as "how baselines will be established and controlled" is the objective of "Initiating a Project" process.
upvoted 1 times
...
peppe
3 years, 1 month ago
C is correct
upvoted 1 times
...
Martin77
3 years, 7 months ago
C - Initiating a Project. One of the objectives of this process is to define how baselines will be established and controlled . Reference - Prince2 manual, 16.2
upvoted 3 times
...
Mehan
3 years, 10 months ago
option B is correct because PID is produced in the directing stage. PID defines the project and forms the basis for the managing and assessment of overall project success. Ref.A.20
upvoted 1 times
DS001
3 years, 7 months ago
PID is created in Initiating a project process
upvoted 2 times
...
...
Becks89
4 years ago
The Starting up project uses Baseline Management Products, one of them is the Project Brief. Therefore D is the correct option.
upvoted 2 times
...
AgnesM
4 years ago
Change control approach is defined during Initiating a project process, therefore option C seems to be correct.
upvoted 2 times
...
sohrabiani
4 years, 1 month ago
I think C should be correct - In SU we do not do anything about Baselines since the initiation is not authorized by DP yet
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...