Which is a purpose of a quality register?

  • A. To record cross-references to issues relating to the quality of the products
  • B. To record the date a completed work package was received
  • C. To provide the status of quality activities carried out for completed products
  • D. To capture quality concerns about completed products
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MarkNeedsToGo
2 days, 10 hours ago
Selected Answer: C
Why is B highlighted??!!!
upvoted 1 times
...
Examcollectorthanos
1 month, 2 weeks ago
c = correct; While the other options might be indirectly related, they are not the main purpose: A. To record cross-references to issues relating to the quality of the products: Issues are typically recorded in a separate issue register or log. B. To record the date a completed work package was received: This information might be found in other project documents, such as the daily log or progress reports. D. To capture quality concerns about completed products: While concerns might be mentioned, the primary focus is on tracking the status of quality activities.
upvoted 1 times
...
bes_i
5 months, 1 week ago
Selected Answer: C
C. A quality register is used to document the quality control activities and status for the project's products. It helps track and manage quality-related activities and issues throughout the project, ensuring that the deliverables meet the required quality standards.
upvoted 1 times
...
AliSami
2 years, 8 months ago
C. is the correct answer
upvoted 2 times
...
Martin77
3 years, 8 months ago
The quality register is updated to reflect (in summary form) the actual results from the quality activities. The quality register provides key audit and assurance information, relating what was planned and agreed (in the quality management approach and product descriptions) to the quality activities actually performed . prince2 guide, 8.2 C should be correct
upvoted 2 times
...
Wombat1987
3 years, 9 months ago
The correct answer is C. Since it has nothing to do with "issues". https://prince2.wiki/management-products/quality-register/ I like to say that a Quality Register does three things: Provides an overview of the planned quality activities and provides a unique reference for each quality activity. Provides an overview on the status of all quality activities and a pointer to the quality records. And at the end of the project, it provides a history of all quality activities that have taken place and all results.
upvoted 2 times
...
Farbod
3 years, 10 months ago
C is correct answer. "Quality register: A quality register is used to summarize all the quality management activities that are planned or have taken place, and provides information for the end stage reports and end project report."
upvoted 3 times
...
Constanza
3 years, 11 months ago
C is the correct answer
upvoted 2 times
...
Mehan
3 years, 11 months ago
A seems to be a more precise answer
upvoted 1 times
...
Shanise
4 years, 3 months ago
C is correct.
upvoted 4 times
...
asalim
4 years, 4 months ago
C is the correct answer. A quality register is used to summarize all the quality management activities that are planned or have taken place, and provides information for the end stage reports and end project report
upvoted 4 times
...
Lenlenlen
4 years, 5 months ago
A it is
upvoted 1 times
...
Vikce
4 years, 5 months ago
agree, A is correct
upvoted 1 times
...
GetRaj
4 years, 5 months ago
A seems to be correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago