Which statement about project roles is CORRECT?

  • A. The project organization must be defined using the roles and responsibilities in PRINCE2
  • B. The project team structure defined in PRINCE2 must be used, but other roles may be added
  • C. The project board roles defined in PRINCE2 must be used, but other roles can be defined as required
  • D. Any role can be defined as required the responsibilities defined in PRINCE2 are fulfilled
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
GetRaj
Highly Voted 4 years, 4 months ago
D seems to be correct
upvoted 8 times
...
Vikce
Highly Voted 4 years, 4 months ago
D is correct
upvoted 6 times
...
skillfulsatellite
Most Recent 5 days, 1 hour ago
Selected Answer: D
The correct answer is: D. Any role can be defined as required if the responsibilities defined in PRINCE2 are fulfilled Explanation: PRINCE2 is a flexible framework that provides a set of roles and responsibilities for effective project management. However, it does not prescribe a rigid structure for the project organization.
upvoted 1 times
...
D; Here's why the other options are less accurate: A & B: These options suggest a rigid adherence to the PRINCE2 structure, which is not in line with the principle of tailoring. C: While the project board roles (Executive, Senior User, Senior Supplier) are crucial in PRINCE2, there's still flexibility to add or adapt other roles as needed. Key takeaway: PRINCE2 provides a solid foundation, but it allows you to adapt the project team structure to suit your specific needs. The focus is on ensuring that all the necessary responsibilities are covered, regardless of the exact titles or structure you choose.
upvoted 1 times
...
The answer is D. Any role can be defined as required as long as the responsibilities defined in PRINCE2 are fulfilled. PLEASE CORRECT THESE ANSWERS
upvoted 1 times
...
Nugi
3 years, 4 months ago
Definitely the answer is D. Reference: In order to be flexible and meet the needs of different environments and different project sizes, PRINCE2 defines a set of roles that need to be undertaken, together with the responsibilities of each of those roles. PRINCE2 does not define jobs to be allocated to people on a one-to-one basis. Roles can be shared or combined according to the project’s needs, but the responsibilities must always be allocated.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...