B; Why the other options are not correct:
A. The project manager: The project manager manages the project on a day-to-day basis, but they don't have the authority to appoint project board members.
C. Corporate, program management, or the customer: While these entities may have an interest in the project, the executive has the ultimate responsibility for appointing the senior user.
D. Project assurance: Project assurance provides independent oversight and advice, but they don't have the authority to appoint project board members.
Key takeaway: In a PRINCE2 project, the executive, as the chair of the project board, is responsible for appointing the senior user to ensure effective representation of user needs and benefits realization.
7.2.1.2 The executive will then be responsible for designing and appointing the
rest of the project management team, including the other members of the project board.
PRINCE2 MAnual. Ref.C.2.1:
In addition to the project board’s collective responsibilities, the executive
will:
design and appoint the project management team (in particular the
project manager)
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
2 weeks agoomande
1 year agoMEHREEN1985
2 years agopeppe
3 years, 1 month agoMehan
3 years, 10 months agoKiana
4 years, 3 months agoGetRaj
4 years, 4 months ago