Decisions regarding the tailoring of the project should be recorded in the B. Project Initiation Documentation (PID).
The PID is a key document in project management that outlines the project's objectives, scope, deliverables, and governance. It also includes details on how the project will be managed, including any tailoring of processes, procedures, or methodologies to suit the specific needs of the project. This ensures that all stakeholders are aligned and aware of how the project will be executed.
Correct answer is PID;
Why the other options are less suitable:
A. Project brief: The project brief is a high-level document that triggers the project. It doesn't go into the detail needed to record tailoring decisions.
C. Project mandate: Similar to the project brief, the project mandate authorizes the project but doesn't typically include specific tailoring details.
D. Stage plan: Stage plans focus on the activities and deliverables within a specific stage, not the overall tailoring of the project management approach.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
ejaymac
Highly Voted 4 years, 7 months agoGetRaj
Highly Voted 4 years, 7 months agoselimbeyhan
Most Recent 3 weeks, 4 days agoExamcollectorthanos
3 months, 2 weeks agogauthier59
3 months, 2 weeks agobes_i
7 months, 1 week agoomande
1 year, 3 months agoKing_Laps
2 years, 3 months agoMehan
4 years, 1 month agoLenlenlen
4 years, 7 months ago