Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 220 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 220
Topic #: 1
[All PRINCE2-Foundation Questions]

What problem may occur if projects are not aligned with corporate business strategy?

  • A. The control of projects may be poor
  • B. The outputs may be of poor quality
  • C. The objectives of different projects may overlap
  • D. The project management approaches used may differ
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
GetRaj
Highly Voted 4 years, 4 months ago
Option C is correct
upvoted 10 times
...
Examcollectorthanos
Most Recent 2 weeks ago
C. The objectives of different projects may overlap. Here's why: Resource Conflicts: If projects aren't aligned, you might end up with multiple projects competing for the same resources (people, budget, equipment) at the same time. This can lead to delays, cost overruns, and overall inefficiency.
upvoted 1 times
...
Examcollectorthanos
2 weeks, 2 days ago
I had B seems most logical
upvoted 1 times
...
HelgeFFM
10 months, 2 weeks ago
Selected Answer: C
I would also say C
upvoted 1 times
...
omande
1 year ago
Selected Answer: C
Textbook pp. 21: "Poor alignment with corporate, programme management or customer strategies can also result in organizations having a portfolio of projects that have mutually inconsistent or duplicated objectives."
upvoted 1 times
...
RznNsr
1 year, 3 months ago
Selected Answer: B
I hope its B
upvoted 1 times
...
Martin77
3 years, 7 months ago
D is the correct answer: "corporate, programme management or customer standards These are overarching standards to which the project must adhere. They will influence the four project approaches (communication management, change control, quality management and risk management) and the project controls." reference prince2 guide glossary on corporate, programme management or customer standards
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...