exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 261 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 261
Topic #: 1
[All PRINCE2-Foundation Questions]

What is a goal of the 'implement' step within the recommended risk management procedure?

  • A. To prepare specific management responses to identified risks
  • B. To monitor the effectiveness of actioned risk responses
  • C. To estimate the risk to the project in terms of probability and impact
  • D. To communicate information related to the risks faced by the project
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Shmell
Highly Voted 4 years, 7 months ago
I believe this answer should be B - Planned risk responses need to be actioned, their effectiveness monitored and corrective action taken where responses do not match expectations.
upvoted 14 times
...
selimbeyhan
Most Recent 3 weeks, 3 days ago
Selected Answer: A
A. To prepare specific management responses to identified risks The goal of the 'implement' step within the recommended risk management procedure is to prepare and execute specific management responses to address the identified risks. This step involves taking action to mitigate, avoid, transfer, or accept risks based on the risk management plan. It ensures that risks are actively managed to minimize their impact on the project. The other options describe goals of different steps in the risk management procedure: B. To monitor the effectiveness of actioned risk responses is part of the 'monitor and control' step. C. To estimate the risk to the project in terms of probability and impact is part of the 'assess' step. D. To communicate information related to the risks faced by the project is part of the 'communicate' step.
upvoted 1 times
...
Examcollectorthanos
3 months, 2 weeks ago
Answer = B. A. To prepare specific management responses to identified risks: This is done in the 'plan' step.   C. To estimate the risk to the project in terms of probability and impact: This is done in the 'assess' step. D. To communicate information related to the risks faced by the project: This is an ongoing activity throughout the risk management process, not just within the 'implement' step.
upvoted 1 times
...
Ppp333
1 year, 5 months ago
Selected Answer: B
10.4.4 Planned risk responses need to be actioned, their effectiveness monitored and corrective action taken where responses do not match expectations.
upvoted 1 times
...
RznNsr
1 year, 5 months ago
Selected Answer: B
B is right
upvoted 1 times
...
peppe
3 years, 4 months ago
B is correct
upvoted 2 times
...
Martin77
3 years, 10 months ago
Planned risk responses need to be actioned, their effectiveness monitored and corrective action taken where responses do not match expectations. Prince2 manual, 10.4.4. The correct answer is B
upvoted 2 times
...
Wombat1987
3 years, 10 months ago
The correct answer is B. https://prince2.wiki/theme/risk/ Step 4: Implement the Responses Forecast. The main thing to decide in this step is: Who is going to monitor these Risks? (Risk Owner). Who is going to carry out the planned Risk Responses? (Risk Actionee).
upvoted 4 times
...
Farbod
3 years, 12 months ago
(A) is correct answer "Implement: refers to the systematic application of procedures to the tasks of identifying and assessing risks, and then planning and implementing risk responses." (B) is For risk management to work effectively, risks will need to be:(Identified, Assessed, Planned, Controlled) B is description of Controlled.
upvoted 2 times
...
Mi
4 years ago
is it not B?
upvoted 2 times
...
justin1234
4 years, 2 months ago
i think A is 'Plan'
upvoted 1 times
...
PrincessPenguin
4 years, 3 months ago
Isn't it A?
upvoted 1 times
...
ejaymac
4 years, 7 months ago
I am leaning towards A
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago