This answer is C - define the management actions that will be put in place to ensure that the project's outcomes are achieved and confirm that the project's benefits are realised
C. To define the actions required to confirm the project's benefits are realized
The Business Case theme in PRINCE2 focuses on ensuring that the project remains viable and aligned with its objectives. A minimum requirement for applying this theme is to define the actions needed to confirm that the project's benefits are realized. This ensures that the project delivers value and justifies the investment. The other options (A, B, and D) are related to monitoring and reporting but are not the minimum requirement for applying the Business Case theme.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Shmell
Highly Voted 4 years, 1 month agoselimbeyhan
Most Recent 3 weeks, 4 days agoTaiH
7 months, 1 week agoRznNsr
1 year agoRznNsr
1 year agoMartin77
3 years, 4 months agosohrabiani
3 years, 10 months agoShanise
3 years, 11 months agoLenlenlen
4 years ago