Exam PRINCE2-Foundation topic 1 question 217 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 217
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is a purpose of the 'initiating a project' process?

  • A. To produce a stage plan for each stage of a multi-stage project
  • B. To enable the project board to decide whether it is worthwhile to initiate a project
  • C. To provide a fixed point at which acceptance for the project product is confirmed
  • D. To enable an organization to understand the work needed to deliver the project's products
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
peppe
Highly Voted 3 years, 1 month ago
D correct
upvoted 6 times
...
TaiH
Most Recent 10 months, 1 week ago
Selected Answer: D
It must be D. See other comments
upvoted 1 times
...
Haranp12
1 year ago
Selected Answer: D
D The purpose of the initiating a project process is to establish solid foundations for the project, enabling the organization to understand the work that needs to be done to deliver the project’s products before committing to a significant spend
upvoted 1 times
...
Testeurtest
1 year, 3 months ago
Selected Answer: D
Purpose The purpose of the Initiating a Project process is to understand the work that needs to be done to deliver the required products.
upvoted 1 times
...
renza
1 year, 9 months ago
Selected Answer: D
D is the right answer
upvoted 1 times
...
Chucky2
1 year, 11 months ago
Selected Answer: D
D is correct
upvoted 2 times
...
Martin77
3 years, 7 months ago
16.1 prince2 manual : The purpose of the initiating a project process is to establish solid foundations for the project, enabling the organization to understand the work that needs to be done to deliver the project's products before committing to a significant spend. D is correct
upvoted 1 times
...
Wombat1987
3 years, 7 months ago
The correct answer is D. https://prince2.wiki/processes/initiating-a-project/ The purpose of the Initiating a Project process is to understand the work that needs to be done to deliver the required products. This understanding is needed before deciding to continue with the project.
upvoted 3 times
...
Mehan
3 years, 10 months ago
definitely, D is the correct answer. Project manual ref.16.1
upvoted 2 times
...
sohrabiani
4 years, 1 month ago
D is correct and B is NOT the answer since authorizing the initiating of the project is already done in IP
upvoted 2 times
...
MaximeHU
4 years, 2 months ago
should be c to me
upvoted 1 times
...
Shanise
4 years, 2 months ago
Agree. It should be D.
upvoted 2 times
...
Lenlenlen
4 years, 4 months ago
it should be D
upvoted 2 times
...
ejaymac
4 years, 4 months ago
I agree also. The answer is D
upvoted 2 times
...
Shmell
4 years, 4 months ago
I agree with Andrius - the answer is D
upvoted 4 times
...
Andrius651
4 years, 5 months ago
Option B is incorrect. That is the purpose of Starting Up a Project Process.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.