The following Activities are to be done in the Starting Up a Project process:
- Appoint the Executive and the Project Manager.
- Capture Previous Lessons.
- Design and appoint the project management team.
- >>> Prepare the outline Business Case and create the Project Product Description (PPD). The PPD is a description of the main product that will be produced
- Select the project approach and assemble the Project Brief.
- Planning the Initiation stage.
c is the right answer
these r the steps:
1-Writing a project product description
2- Creating a product breakdown structure
3-Writing product descriptions
4-Conducting a product flow diagram
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Andrius651
Highly Voted 4 years, 4 months agoLenlenlen
Highly Voted 4 years, 3 months agotarikaygul
Most Recent 10 months, 1 week agoTesteurtest
1 year, 2 months agosdoukkal
1 year, 7 months agorenza
1 year, 8 months agoChucky2
1 year, 10 months agopeppe
3 years agoSunnie999
3 years, 1 month agokal5
3 years, 1 month agoPMBT_1017
3 years, 4 months agoMehan
3 years, 9 months agosohrabiani
4 years ago