exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 223 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 223
Topic #: 1
[All PRINCE2-Foundation Questions]

Which statements about quality assurance and project assurance are CORRECT?
1. They are both independent of the project manager
2. They are both the responsibility of the project board
3. They are both independent from the project management team
4. They both assure that applicable standards are being used

  • A. 1 and 2
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 4
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
johnzoids
Highly Voted 4 years, 1 month ago
Its D (1,4)
upvoted 9 times
...
sohrabiani
Highly Voted 3 years, 9 months ago
D is correct - Statement 3 is not right because they are not both independent from PMT - Project assurance is by PB which is part of PMT
upvoted 5 times
...
TaiH
Most Recent 6 months ago
Selected Answer: D
It is D
upvoted 1 times
...
HelgeFFM
6 months, 1 week ago
Selected Answer: D
I would also say D
upvoted 1 times
...
Haranp12
9 months, 3 weeks ago
Selected Answer: D
Option 1 is definitely correct. And 4 is a better option than 3
upvoted 2 times
...
Testeurtest
11 months ago
Selected Answer: D
Quality Assurance This is like Project Assurance but the focus is on Quality in the organization and not just quality related to the project. It is to make sure that the planned Quality activities are done. Provides a way to get an independent review of the Quality process; Checks to see that it complies with company Quality standards; and Ensures that Quality processes are in place. Project Assurance is the responsibility of the Project Board, while the Corporate or Programme Management is responsible for Quality Assurance. You can also say that the role Quality Assurance is outside the project management team while Project Assurance is within the project management team
upvoted 2 times
...
RznNsr
11 months ago
D IS RIGHT
upvoted 2 times
...
MartijnRM
1 year ago
D IS RIGHT
upvoted 2 times
...
peppe
2 years, 9 months ago
D is correct
upvoted 4 times
...
Prince_Gem
4 years, 1 month ago
Quality assurance are not part of Project management team
upvoted 2 times
Mehan
3 years, 6 months ago
D is the correct answer
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago