Question #: 223
Topic #: 1
[All PRINCE2-Foundation Questions]

Which statements about quality assurance and project assurance are CORRECT?
1. They are both independent of the project manager
2. They are both the responsibility of the project board
3. They are both independent from the project management team
4. They both assure that applicable standards are being used

  • A. 1 and 2
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 4
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
johnzoids
Highly Voted 4 years, 5 months ago
Its D (1,4)
upvoted 9 times
...
sohrabiani
Highly Voted 4 years, 1 month ago
D is correct - Statement 3 is not right because they are not both independent from PMT - Project assurance is by PB which is part of PMT
upvoted 5 times
...
TaiH
Most Recent 10 months, 1 week ago
Selected Answer: D
It is D
upvoted 1 times
...
HelgeFFM
10 months, 2 weeks ago
Selected Answer: D
I would also say D
upvoted 1 times
...
Haranp12
1 year, 1 month ago
Selected Answer: D
Option 1 is definitely correct. And 4 is a better option than 3
upvoted 2 times
...
Testeurtest
1 year, 3 months ago
Selected Answer: D
Quality Assurance This is like Project Assurance but the focus is on Quality in the organization and not just quality related to the project. It is to make sure that the planned Quality activities are done. Provides a way to get an independent review of the Quality process; Checks to see that it complies with company Quality standards; and Ensures that Quality processes are in place. Project Assurance is the responsibility of the Project Board, while the Corporate or Programme Management is responsible for Quality Assurance. You can also say that the role Quality Assurance is outside the project management team while Project Assurance is within the project management team
upvoted 2 times
...
RznNsr
1 year, 3 months ago
D IS RIGHT
upvoted 2 times
...
MartijnRM
1 year, 5 months ago
D IS RIGHT
upvoted 2 times
...
peppe
3 years, 1 month ago
D is correct
upvoted 4 times
...
Prince_Gem
4 years, 5 months ago
Quality assurance are not part of Project management team
upvoted 2 times
Mehan
3 years, 10 months ago
D is the correct answer
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...