D is the right answer
A. To approve the initiation stage (directing)
B. To select the project mandate (before starting up the project and selected by corporate mgmt)
C. To define the project quality management approach (initiation)
D. To appoint the project management team (starting up)
D is the right answer
A. To approve the initiation stage (directing)
B. To select the project mandate (before starting up the project and selected by corporate mgmt)
C. To define the project quality management approach (initiation)
D. To appoint the project management team (starting up)
D
14.2:
The objective of the starting up a project process is to ensure that:
● there is a business justification for initiating the project (documented in an outline business case)
● all the necessary authorities exist for initiating the project
● sufficient information is available to define and confirm the scope of the project (in the form of a project brief)
● the various ways the project can be delivered are evaluated and a project approach selected
● individuals are appointed who will undertake the work required in project initiation and/or will take significant
project management roles in the project
● the work required for project initiation is planned (documented in a stage plan)
● time is not wasted initiating a project based on unsound assumptions regarding the project’s scope,
timescales, acceptance criteria and constraints.
Corretct answer is D.
A. To approve the initiation stage is in DIrecting a project process
B. To select the project mandate doesnt have any sense in any process
C. To define the project quality management approach is a initiating a process task,
I would have said A because in chapter 14.1 the very first sentence is this: "The purpose of the starting up a project process is to ensure that the prerequisites for initiating a project* are in place [...]". So *this is an actual stage, therefor I would say A is correct.
As per Figure 14.1 Overview of starting up a project (Prince2 guide) appoint the executive and project manager is the first step (which are both part of the Project Management team). D seems to be correct here
Sure, but if you look a second time, you'll see that they are only one part of the entire process called "Starting up a project", you see the last output of this process is "Plan the initiation stage", so after this last one so-called "Starting up a project" process is set, the next stage will be started
The correct answer is D.
https://prince2.wiki/processes/starting-up-a-project/
The following Activities are to be done in the Starting Up a Project process:
...
Design and appoint the project management team.
...
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Prince_Gem
Highly Voted 4 years, 5 months agoTesteurtest
Highly Voted 1 year, 3 months agoRznNsr
Most Recent 1 year, 3 months agorenza
1 year, 9 months agoRisto83
1 year, 11 months agolucafranco
2 years, 10 months agoSteven2021
2 years, 12 months agopeppe
3 years, 1 month agoMartin77
3 years, 7 months agoSteven2021
2 years, 12 months agoDS001
3 years, 7 months agoWombat1987
3 years, 8 months agoMehan
3 years, 10 months agosohrabiani
4 years, 1 month agoMaximeHU
4 years, 2 months agoLenlenlen
4 years, 4 months agoejaymac
4 years, 4 months agoVikce
4 years, 4 months ago