Question #: 203
Topic #: 1
[All PRINCE2-Foundation Questions]

What should the 'managing product delivery' process ensure?
1. That the planned products meet their quality criteria
2. That the stage plan is kept up to date
3. That the project board is provided with progress information
4. That the planned products are delivered within tolerance

  • A. 1 and 2
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 4
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vikce
Highly Voted 4 years, 4 months ago
correct answer is D
upvoted 10 times
...
tarikaygul
Most Recent 11 months, 1 week ago
c is correct Managing product delivery process ensures that: •Work on products allocated to the team is authorized and agreed •Team Managers, team members, and suppliers are clear as to what is to be produced and what is the expected effort, cost, or timescales •The planned products are delivered to expectations and within tolerance •Accurate progress information is provided to the Project Manager at an agreed frequency to ensure that expectations are managed
upvoted 2 times
...
Adrienne
1 year, 2 months ago
Selected Answer: D
D, as this is carried out in the Project team and is not a Project manager responsibility
upvoted 2 times
...
Testeurtest
1 year, 3 months ago
Selected Answer: D
D is a better answer
upvoted 1 times
...
RD27
1 year, 4 months ago
Selected Answer: D
D is the correct answer imho
upvoted 1 times
...
renza
1 year, 9 months ago
Selected Answer: D
D is the right answer
upvoted 1 times
...
Sunnie999
3 years, 2 months ago
Correct answer should be D. As the accurate progress information is provided to the Project Manager instead of Project Board.
upvoted 2 times
...
Wombat1987
3 years, 7 months ago
The correct answer is D. This process is a "handshake" between PM and TM. It consists of three stages: you agree with a work package, you execute it, you deliver it. There is nothing about project board. https://prince2.wiki/processes/managing-product-delivery/ Managing Product Delivery Activities Accepting a Work Package: The Team Manager accepts the Work Package from the Project Manager and creates the Team Plan to manage the development of the products. Executing a Work Package: The team produces the products, requests the quality checks, obtains approval, and reports to the Project Manager using the Checkpoint Report. Delivering a Work Package: Delivering a Work Package is delivering proof that the products are complete. This involves ensuring that the Quality Register is updated, that approvals are done, that products are delivered as described in the Change Control Approach , and that the Project Manager is notified.
upvoted 4 times
...
KeithN
3 years, 9 months ago
I think No.3 is part of conrolling of stage too.
upvoted 1 times
...
Panzerknacker
4 years ago
it should be D
upvoted 3 times
...
AgnesM
4 years ago
Correct answer is D. Managing a product delivery process is delegated to team manager, who reports to Project manager...
upvoted 2 times
...
sohrabiani
4 years, 1 month ago
PB will not be informed about progress via MP, and it will be done via CS
upvoted 1 times
...
Lenlenlen
4 years, 4 months ago
it should be D
upvoted 4 times
...
Prince_Gem
4 years, 5 months ago
surely No. 3 is part of controlling process ?
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...