The answer is C.
PRINCE2 recommends, but does not mandate, a risk management procedure based on Management of Risk: Guidance for Practitioners (Office of Government Commerce, 2010):
Identify (context and risks)
Assess (estimate and evaluate)
Plan
Implement
Communicate.
'Issues' is the term used in PRINCE2 for changes therefore I think the answer A is incorrect as it refers to risk management, not change management. Answer C makes more sense.
Should be C. refer 10.4.5 Communication should be undertaken continually. The ‘communicate’ step ensures that information related to
the threats and opportunities faced by the project is communicated both within the project and externally to stakeholders.
PRINCE2 MAnual Ref.10.2
ensure that project risks are identified, assessed, managed and
reviewed throughout the project lifecycle. I think the correct answer is B.
The communication of the risk is part of the Risk management approach, which is also a necessary requirement, but for the approach.
C should be correct as stated in section10.3.2 : 'Communicate', the fith step, operates in parallel as the outputs of any of the other steps may need to be communicted to stakesholders at any point in the process'
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Wombat1987
Highly Voted 3 years, 6 months agoDS001
Highly Voted 3 years, 6 months agotarikaygul
Most Recent 10 months, 1 week agoPescaruM
10 months, 3 weeks agoHaranp12
11 months, 3 weeks agoSGN63
1 year, 7 months agoKeanoD
2 years, 1 month agojj0097
2 years, 3 months agopeppe
3 years agorezab
3 years, 8 months agoMehan
3 years, 9 months agoPanzerknacker
3 years, 11 months agosohrabiani
4 years agoGLKTYI
4 years, 3 months agoGLKTYI
4 years, 3 months agoPrince_Gem
4 years, 4 months ago