Correct Answer is C.
7.1 The four levels of management: Corporate, programme management or the customer This level
sits above the project management team but will be responsible for
commissioning the project, including identifying the executive and
defining the project-level tolerances within which the project board will
work. This information should, if possible, be recorded in the project
mandate.
The tolerances are set at one level above which they apply and are reported to this level. Corporate or Programme Management set the overall project tolerances. The Project Board is responsible for the project operating within these tolerances.
- setting tolerances
• Corporate management: set project tolerances
• project board: set stage tolerances
• project manager agrees with team manager: set workpackages tolerances
Definitely C.
● Corporate, programme management or the customer This level sits above the project management team but will be responsible for commissioning the project, including identifying the executive and defining the project-level tolerances within which the project board will work. This information should, if possible, be recorded in the project mandate.
C is correct - Corporate, programme
management or the customer set the project tolerances (mentioned in section 9.2.2 table 9.1 in the Plans theme and a few other places in the manual)
The correct answer is C.
https://www.prince2primer.com/project-board-and-project-manager-prince2-controls/
As part of management by exception, corporate or programme management will have set project level tolerances. The project board need to agree stage level tolerances and optionally the project manager may set tolerances at work package level (although this may not need to be done at this point in time).
The answer is Coporate/Programmme. Please you guys should do your research thoroughly before you mislead us. Some answers to the questions seen earlier were wrong.
CPC will set the Project tolerance so accordingly in case of exceeding those tolerances, the case be escalated to them
PM will set the work package tolerance
Project board set stage tolerance, project manager set work package tolerance. Corporate program set project level tolerance. So many misleading on these exam practice
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Ppp333
1 year, 2 months agoAdrienne
1 year, 2 months agoRznNsr
1 year, 3 months agoSGN63
1 year, 8 months agorenza
1 year, 9 months agoMrMooMooBee
1 year, 10 months agojj0097
2 years, 4 months agoNugi
3 years, 4 months agoMartin77
3 years, 7 months agoDS001
3 years, 7 months agoWombat1987
3 years, 8 months agodemmy22
3 years, 10 months agoMehan
3 years, 10 months agosohrabiani
4 years, 1 month agoLenlenlen
4 years, 4 months agoGLKTYI
4 years, 4 months agoejaymac
4 years, 4 months ago